Capacity and planned hires

What this page is — A grid of net plannable hours — one row per person or planned hire, one column per time box of the scenario — computed from the organisation's working calendar, holidays, approved leave, each person's allocation and the project's focus factor. What it is for — Knowing how many hours a sprint really has before you fill it, and seeing at a glance who is over or under. The problem it solves — Sprint capacity is usually a guess of "ten people × ten days × eight hours". That number ignores public holidays in a zone, approved leave, part-timers, meetings, and people who have not been hired yet. The grid replaces the guess with a derivation you can read in a tooltip.


Route: /org/tasks/planning?tab=capacity · Permissions: View planning (read the grid), Manage planning (overrides, include/exclude, skill areas, planned hires) Module: Planning · Entry points: Planning → Capacity · Capacity → Add planned hire · Capacity → Link existing hire · a hire row's ⋯ menu · Quick create → Planned hire · Cockpit → Planning Pulse → Planned hires


1. How a cell is computed​

For each person and time box the platform walks the calendar day by day and then applies three factors. The tooltip on every cell prints exactly this:

working days = gross days − holiday days − leave days
× hours per day × allocation × focus factor = computed hours
Figure 1 — 1 A cell's tooltip: the derivation lines, the load and the Source line.
InputWhere it comes fromNotes
Working days and hours per dayThe organisation work week for the person's zone (else the organisation-wide row); hours = end − start − breakFalls back to the calendar settings, then to the attendance rules' standard hours, then to Monday–Friday, 8 hours
Hours per day overrideProject settings → PlanningReplaces the calendar's hours when set
HolidaysOrganisation holidays for the person's zone or organisation-wideOptional (restricted) holidays count only when Include optional holidays is on
LeaveApproved leave applicationsA half day deducts 0.5
AllocationThe member's hours per week ÷ the organisation's working week (working days × hours per day), capped at 100%Set with Edit member capacity on the Roadmap or on Define; a planned hire uses its own hours per week
Focus factorProject default (0.80), or the time box's own value from the Goals tabThe share of a day that is plannable

The tooltip ends with a Source line naming which calendar rule applied, so a surprising number can be traced.


2. Why you would use it​

  • Catch the sprint where half the team is on leave before you plan it full.
  • Give a part-time colleague a fair share automatically instead of remembering to halve their load.
  • Keep a person on the roster but exclude them from one sprint (secondment, training) without editing their allocation.
  • Model a hire that has not happened, then hand the work over the day they join.

3. Reading the grid — step by step​

Step 1 · Rows, columns, totals​

Rows are the project's members followed by planned hires. A hire row carries a status chip (see Managing a hire from its row, below) and, for anyone with Manage planning, a ⋯ menu. Columns are the time boxes of the scenario, each with its date range. The last row totals net hours per column against the planned load, with a state chip.

Figure 2 — The capacity grid: 1 member rows, 4 include/exclude tick box, 5 column totals with state chips, 6 Add planned hire (beside Recompute and Link existing hire). Pips 2 (hire row) and 3 (overridden cell) do not appear in this example.

Step 2 · States​

StateRuleColour
Overload ÷ net is above the overload ratio (1.2 by default, shared with the Risk radar)Red
Underload ÷ net is below the underload ratio (0.60 by default)Amber
OKBetween the twoGreen
No capacityNet hours are zero but tasks are planned on the personGrey
ExcludedThe person is switched off for this time boxGrey

The load bar under every column header is drawn to 125% of net, with a mark at 100%.

Step 3 · Override a cell​

Click a cell and type net hours — net days on a project that plans in days; the grid, the totals and every tooltip figure read in the project's unit, and the derivation still shows hours per day (Enter saves, Escape cancels). Overridden cells are shown in bold; the tooltip prints Override: N h under the derivation, and the small reset icon clears it. Overrides survive Recompute and are carried into the next scenario committed for the same time box.

Step 4 · Include or exclude​

The circle beside each cell toggles the person in or out of that time box. Excluded rows carry no capacity and no load for that column.

Step 5 · Skill area​

The select on each row assigns one of the project's skill areas (from Project settings → Planning). It is a label to help you match work to people; it does not restrict assignment.

Step 6 · The value of a time box​

When the project values its work (Settings → Money), each time box's totals carry what it is worth and how much of that is already done — the money side of the same picture the load bars show. A contractor row reads its day rate too, so an over-full crew and an over-priced one are visible in the same place.

Step 7 · Recompute​

Recompute re-runs the calendar for every resource — after a leave request is approved or a holiday added — while keeping overrides, inclusion and skill areas.


4. Planned hires — field reference​

Figure 3 — Add planned hire: name, role, hours per week, zone, availability window, projects.

A planned hire is a placeholder person you can plan against before they exist. Hires live at the organisation level so one requisition can serve several projects.

FieldTypeRequiredNotes
Name / labelTextYese.g. "Backend hire #2"
RoleTextNoShown on cards and in the assignee list
SkillsTagsNoType and press Enter
Hours per weekNumberNoAllocation = hours ÷ 40, capped at 100%
Zone (holidays)Select of leave zones, or No zone (no holidays deducted)NoOnly holidays are deducted — a hire has no leave
Available from · toDatesNoCapacity is clipped to this window; "The end must not be before the start."
ProjectsToggle chips, one per project of the organisationNoThe projects that may plan on this hire; the current project is ticked when the dialog opens
NotesTextNoRequisition id, budget, expected start

Add planned hire — here or on the Define tab, which also shows each hire's Planned as skill — opens the dialog; Add hire creates the hire (Save hire when editing) and, when the current project is ticked, adds it to every time box of the scenario. Link existing hire lists Planned hires in your organisation: Link connects an existing hire to this project, Add to scenario puts an already linked hire on the board.

Three rules never bend:

  1. A hire counts in capacity and load exactly like a member.
  2. A hire is never an assignee. When a scenario is committed, a task planned on a hire stays unassigned on the live board with a planned-hire marker; the commit preview lists these under Tasks planned on hires.
  3. When the person joins, replace the hire with the real member: every open task and draft scenario item planned on the hire moves to that member in each project where they are an active member (other projects are listed as skipped), the hire becomes hired, and the usual assignment notifications go out. Cancelling a hire removes it from every board and leaves its draft scenario items unassigned.

Managing a hire from its row​

Each hire row shows a status chip beside the name — hover it to see the role:

ChipMeaning
ActiveThe hire is still a placeholder; work can be planned on it
Hired → member nameThe hire was replaced by that member; its tasks now belong to them (just Hired if the member's name is unavailable)
CancelledThe requisition was dropped
HireA plain marker, shown when the hire's record cannot be read — for example a hire you can no longer see

The ⋯ menu opens with a line naming the role and status, then three actions. The menu needs Manage planning and works on committed scenarios too, because a hire belongs to the organisation, not to the scenario:

ActionWhat happensAvailable when
EditOpens Edit planned hire with the same fields as Add planned hire. Changing hours per week or the availability window changes capacity on the next RecomputeAlways
Replace with real user…The menu turns into Replace "hire name" with a project member: pick someone in Pick a member (the list is this project's members) and press Replace. Every open task and draft scenario item planned on the hire — in every project the hire is linked to — moves to that member where they are an active member; other projects are skipped. The chip becomes Hired → memberOnly while the hire is Active — otherwise greyed with Only an active hire can be replaced
Cancel hireAsks Cancel planned hire "hire name"? — The hire is marked cancelled and disappears from every board. Draft items planned on it become unassigned; live tasks keep their placement but lose the planned hire. Confirm with Cancel hireOnly while the hire is Active — otherwise greyed with Already hired or Already cancelled

Replacing and cancelling cannot be undone from the grid. To keep planning on a role after cancelling, add a new planned hire.


5. Worked example​

Sprint R3-S2 runs 15–28 Oct, ten working days. Priya is in the Bengaluru zone, which has two holidays in that window, and has one approved half day; her row shows 7.5 working days = 10 gross − 2 holiday − 0.5 leave × 8 h/day × 100% allocation × 80% focus = 48h. Tom works 20 hours a week, so his cell reads 32h at 50% allocation. The team adds the hire "QA hire #1" at 40 hours a week, zone Bengaluru, available from 20 Oct: the hire's cell shows seven working days and 44.8h. The column total reaches Over at 128%; the planner excludes Tom from this sprint (he is on a customer visit) and moves two tasks to the next sprint until it reads OK. In November the QA engineer joins: the planner opens the hire's ⋯ menu, chooses Replace with real user…, picks her, and the chip turns to Hired → Asha; the six open tasks planned on the hire are now assigned to Asha.


6. The admin contract​

  • Hours per week of members is set on the Roadmap's capacity table (Edit member capacity), not in Planning.
  • Holidays, zones, the work week and leave are People / organisation settings; Planning only reads them. A person without a zone gets organisation-wide holidays only.
  • Overload ratio is the Risk radar setting of the project; underload ratio, focus factor, hours per day override and include optional holidays are in Project settings → Planning.
  • Creating, editing, replacing and cancelling hires needs Manage planning.

7. Don't confuse this with…​


8. Troubleshooting​

SymptomCauseFix
Everyone shows Monday–Friday 8 h though the office works SundaysNo work week or calendar settings for the zoneAsk your administrator to set the organisation work week; check the tooltip's Source
A holiday is not deductedIt is an optional holiday, or in another zoneTurn on Include optional holidays, or fix the person's zone
Leave is missing from a cellThe leave is not yet approved, or the scenario was seeded before approvalApprove it, then Recompute
A hire has no hours in a sprintThe sprint lies outside the hire's availability windowAdjust Available from / to
A cell is No capacityNet is zero but tasks are planned thereMove the tasks or include the person
I cannot edit anythingThe scenario is committed, or you lack Manage planningClone the scenario; ask for the permission
Replace with real user… and Cancel hire are greyedThe hire is already hired or cancelledNothing to do; add a new hire if the role is open again
The member I want is not in Pick a memberThe list holds this project's members onlyAdd them to the project first, then replace
After replacing, some tasks still wait on the hireThe member is not an active member of those other projects, so they were skipped — and the hire is now hired, so it cannot be replaced againReassign those tasks by hand in their projects
No ⋯ on a hire rowYou lack Manage planningAsk for the permission